MCDF Detail Project Plans (by week)

 

Week

Task

Done?

 

 

 

 

 

 

 

CY 2007

 

 

Mar 30

Project Restart

Yes

Apr 2

Project staffing / Equipment Shipment

Yes

Apr 9

Project staffing / Equipment Shipment

Yes

Apr 16….

Site Preparation Activities

Yes

…May 14

Site Preparation Activities

Yes

May 21…

Equipment Installation

Yes

…July 30

Equipment Installation

Yes

Aug 6

PDWC ADAM AP Tests

Yes

Aug 13

Cryofracture component checkout/startup

Yes

Aug 20

PDWC ADAM AP Tests

Yes

Aug 27

Cryofracture Integrated Plant initial startup

Yes

Sept 3

Induction heater/dust collection operational tests

Rescheduled

Sept 10

APE-1236 RKS Plant Maintenance

Yes

Sept 17

Induction heater/dust collection operational tests

Cryofracture Integrated Plant Operation – in Air and with LN2

Yes

Rescheduled

Sept 24

APE-1236 RKS RATA tests at MCAAP

Successful

Oct 1

Cryofracture Integrated Plant Operation – in Air and with LN2

Cryofracture Integrated Plant Operation – ADAM QA mines

Yes

Yes

Oct 8

PDWC ADAM AP Tests

Yes

Oct 15

Cryofracture Integrated Plant Operation – ADAM QA mines

Yes

Oct 22

Cryofracture Readiness Review Meeting Oct 23

Cryofracture Integrated Plant Operation – ADAM QA mines

Yes

Limited

Oct 29

Plant Maintenance – installation of air dryer, camera, and robot UPS

Yes but no UPS

Nov 5

Cryofracture Integrated Plant Operation – ADAM QA mines

Start processing induction heater drums from 2004 tests

Yes

Yes

Nov 12

PDWC ADAM AP Tests

Cryofracture non-normal SOP review meeting – Nov 13 & Nov 14

Yes

Yes

Nov 19

Thanksgiving week – no work at plant

Yes

Nov 26

Cryofracture Integrated Plant Operation – ADAM QA mines

Yes

Dec 3

Cryofracture Readiness Review Meeting Dec 4

Yes

Dec 10

PDWC ADAM AP Tests

MCAAP Fuze Demil Program using APE-1236 RKS

Yes

Dec 17

MCAAP Fuze Demil Program using APE-1236 RKS

Yes

Dec 24

MCAAP Fuze Demil Program using APE-1236 RKS

Yes

Dec 31

MCAAP Fuze Demil Program using APE-1236 RKS

Yes

 

 


 

MCDF Detail Project Plans (by week)

 

Week

Task

Done?

 

 

 

 

 

 

 

CY 2008

 

 

Jan 7

Induction heater installation and test

Continue processing induction heater drums from 2004 tests

Cryofracture Integrated Plant Operations – ADAM QA Mines

Yes

Jan 14

MCAAP Fuze Demil Program using APE-1236 RKS (Week #1)

Yes

Jan 22

MCAAP Fuze Demil Program using APE-1236 RKS (Week #2)

Yes

Jan 28

MCAAP Fuze Demil Program using APE-1236 RKS (Week #3)

Cryofracture Readiness Review Meeting – Jan 30 & Jan 31

Yes

Feb 4

MCAAP Fuze Demil Program using APE-1236 RKS (Week #4)

Yes

Feb 11

MCAAP Fuze Demil Program using APE-1236 RKS (Week #5)

Yes

Feb 18

MCAAP APE-1236 RKS Afterburner Repair

Yes

Feb 25

MCAAP APE-1236 RKS Afterburner Repair

Yes

Mar 3

MCAAP Fuze Demil Program using APE-1236 RKS (Week #6)

Yes

Mar 10

Cryofracture Integrated Plant Operations – ADAM QA mines and then transition to ADAM AP Mines.  Plant Walk-thru 3/12/08.

APE-1236 RKS Stand-along/Cryofracture air flow test on 3/14/08.

Yes

Mar 17

Cryofracture Integrated Plant Operations – ADAM AP Mines Test #1 and Test #2 test protocol

APE-1236 Air Flow Balance and Test (3/18/08)

Yes

Mar 24

Cryofracture Integrated Plant Operations – ADAM AP Mines

Yes

Mar 31

Cryofracture Integrated Plant Operations – ADAM AP Mines

Yes

Apr 7

MCAAP Fuze Demil Program using APE-1236 RKS (Week #7)

Yes

Apr 14

MCAAP Fuze Demil Program using APE-1236 RKS

Yes

Dec 26

End of MCAAP Fuze Demil Program using APE-1236 RKS

Yes

                                       

 

 

 

 

 

 

 


 

MCDF Detail Project Plans (by week)

 

Week

Task

Done?

 

 

 

 

 

 

 

CY 2008

 

 

Dec 8

Removal of incline conveyor and isolation blast valve for GA upgrades

Yes

 

 

 

CY 2009

 

 

May 31

Pre-installation inspection

Yes

Apr 6

Shipment of upgraded equipment to MCAAP

Yes

Apr 13

Installation of upgraded equipment

Yes

Apr 20

Installation of upgraded equipment

Yes

Apr 27

Cryofracture Integrated Plant Operations – Equipment testing

MCAAP Ground test (4/27/09) and APE-1236 Mods (4/28/09)

Yes

May 18

No site activity

Yes

May 25

Plant walk-thru/readiness test

APE-1236 RKS stand alone – cryofracture air flow test

Integrated Plant Operations – startup, operation, shutdown

Yes

June 1

No site activity

Yes

June 8

Integrated Plant Operations – process inerts

Integrated Plant Operations – process ADAM QA mines

Integrated Plant Operations – process ADAM AP mines

Yes

June 15

MCAAP prepares for CPT

Yes

June 22

MCAAP prepares for CPT

Yes

June 29

MCAAP prepares for CPT

Yes

July 6

MCAAP prepares for CPT

Yes

July 13

CPT Execution

Yes

July 20

Integrated Plant Operations – process ADAM AP mines

Start DEM/VAL test

Not complete

July 27

No activity

Yes

Aug 3

Meeting at PM-Demil to discuss options

Yes

Aug 10

No activity

Yes

Aug 17

No activity

Yes

Aug 24

No activity

Yes

Aug 31

No activity

Yes

                                     

Additional weeks to be added later as project concludes