MCDF Detail Project Plans (by week)
|
Week |
Task |
Done? |
|
|
|
|
|
|
|
|
|
CY 2007 |
|
|
|
Mar 30 |
Project Restart |
Yes |
|
Apr 2 |
Project staffing / Equipment
Shipment |
Yes |
|
Apr 9 |
Project staffing / Equipment
Shipment |
Yes |
|
Apr 16…. |
Site Preparation Activities |
Yes |
|
…May 14 |
Site Preparation Activities |
Yes |
|
May 21… |
Equipment Installation |
Yes |
|
…July 30 |
Equipment Installation |
Yes |
|
Aug 6 |
PDWC ADAM AP Tests |
Yes |
|
Aug 13 |
Cryofracture component
checkout/startup |
Yes |
|
Aug 20 |
PDWC ADAM AP Tests |
Yes |
|
Aug 27 |
Cryofracture Integrated Plant
initial startup |
Yes |
|
Sept 3 |
Induction heater/dust collection
operational tests |
Rescheduled |
|
Sept 10 |
APE-1236 RKS Plant Maintenance |
Yes |
|
Sept 17 |
Induction heater/dust collection
operational tests Cryofracture Integrated Plant
Operation – in Air and with LN2 |
Yes Rescheduled |
|
Sept 24 |
APE-1236 RKS RATA tests at MCAAP |
Successful |
|
Oct 1 |
Cryofracture Integrated Plant
Operation – in Air and with LN2 Cryofracture Integrated Plant
Operation – ADAM QA mines |
Yes Yes |
|
Oct 8 |
PDWC ADAM AP Tests |
Yes |
|
Oct 15 |
Cryofracture Integrated Plant
Operation – ADAM QA mines |
Yes |
|
Oct 22 |
Cryofracture Readiness Review
Meeting Oct 23 Cryofracture Integrated Plant
Operation – ADAM QA mines |
Yes Limited |
|
Oct 29 |
Plant Maintenance – installation of
air dryer, camera, and robot UPS |
Yes but no UPS |
|
Nov 5 |
Cryofracture Integrated Plant
Operation – ADAM QA mines Start processing induction heater
drums from 2004 tests |
Yes Yes |
|
Nov 12 |
PDWC ADAM AP Tests Cryofracture non-normal SOP review
meeting – Nov 13 & Nov 14 |
Yes Yes |
|
Nov 19 |
Thanksgiving week – no work at
plant |
Yes |
|
Nov 26 |
Cryofracture Integrated Plant
Operation – ADAM QA mines |
Yes |
|
Dec 3 |
Cryofracture Readiness Review
Meeting Dec 4 |
Yes |
|
Dec 10 |
PDWC ADAM AP Tests MCAAP Fuze Demil Program using
APE-1236 RKS |
Yes |
|
Dec 17 |
MCAAP Fuze Demil Program using
APE-1236 RKS |
Yes |
|
Dec 24 |
MCAAP Fuze Demil Program using
APE-1236 RKS |
Yes |
|
Dec 31 |
MCAAP Fuze Demil Program using
APE-1236 RKS |
Yes |
MCDF Detail Project Plans (by week)
|
Week |
Task |
Done? |
|
|
|
|
|
|
|
|
|
CY 2008 |
|
|
|
Jan 7 |
Induction heater installation and
test Continue processing induction
heater drums from 2004 tests Cryofracture Integrated Plant
Operations – ADAM QA Mines |
Yes |
|
Jan 14 |
MCAAP Fuze Demil Program using
APE-1236 RKS (Week #1) |
Yes |
|
Jan 22 |
MCAAP Fuze Demil Program using
APE-1236 RKS (Week #2) |
Yes |
|
Jan 28 |
MCAAP Fuze Demil Program using
APE-1236 RKS (Week #3) Cryofracture Readiness Review
Meeting – Jan 30 & Jan 31 |
Yes |
|
Feb 4 |
MCAAP Fuze Demil Program using
APE-1236 RKS (Week #4) |
Yes |
|
Feb 11 |
MCAAP Fuze Demil Program using
APE-1236 RKS (Week #5) |
Yes |
|
Feb 18 |
MCAAP APE-1236 RKS Afterburner
Repair |
Yes |
|
Feb 25 |
MCAAP APE-1236 RKS Afterburner
Repair |
Yes |
|
Mar 3 |
MCAAP Fuze Demil Program using
APE-1236 RKS (Week #6) |
Yes |
|
Mar 10 |
Cryofracture Integrated Plant Operations
– ADAM QA mines and then transition to ADAM AP Mines. Plant Walk-thru 3/12/08. APE-1236 RKS
Stand-along/Cryofracture air flow test on 3/14/08. |
Yes |
|
Mar 17 |
Cryofracture Integrated Plant Operations
– ADAM AP Mines Test #1 and Test #2 test protocol APE-1236 Air Flow Balance and
Test (3/18/08) |
Yes |
|
Mar 24 |
Cryofracture Integrated Plant
Operations – ADAM AP Mines |
Yes |
|
Mar 31 |
Cryofracture Integrated Plant
Operations – ADAM AP Mines |
Yes |
|
Apr 7 |
MCAAP Fuze Demil Program using
APE-1236 RKS (Week #7) |
Yes |
|
Apr 14 |
MCAAP Fuze Demil Program using
APE-1236 RKS |
Yes |
|
Dec 26 |
End of MCAAP Fuze Demil Program
using APE-1236 RKS |
Yes |
MCDF Detail Project Plans (by week)
|
Week |
Task |
Done? |
|
|
|
|
|
|
|
|
|
CY 2008 |
|
|
|
Dec 8 |
Removal of incline conveyor and
isolation blast valve for GA upgrades |
Yes |
|
|
|
|
|
CY 2009 |
|
|
|
May 31 |
Pre-installation inspection |
Yes |
|
Apr 6 |
Shipment of upgraded equipment to
MCAAP |
Yes |
|
Apr 13 |
Installation of upgraded
equipment |
Yes |
|
Apr 20 |
Installation of upgraded
equipment |
Yes |
|
Apr 27 |
Cryofracture Integrated Plant Operations
– Equipment testing MCAAP Ground test (4/27/09) and
APE-1236 Mods (4/28/09) |
Yes |
|
May 18 |
No site activity |
Yes |
|
May 25 |
Plant walk-thru/readiness test APE-1236 RKS stand alone –
cryofracture air flow test Integrated Plant Operations –
startup, operation, shutdown |
Yes |
|
June 1 |
No site activity |
Yes |
|
June 8 |
Integrated Plant Operations –
process inerts Integrated Plant Operations –
process ADAM QA mines Integrated Plant Operations –
process ADAM AP mines |
Yes |
|
June 15 |
MCAAP prepares for CPT |
Yes |
|
June 22 |
MCAAP prepares for CPT |
Yes |
|
June 29 |
MCAAP prepares for CPT |
Yes |
|
July 6 |
MCAAP prepares for CPT |
Yes |
|
July 13 |
CPT Execution |
Yes |
|
July 20 |
Integrated Plant Operations –
process ADAM AP mines Start DEM/VAL test |
Not complete |
|
July 27 |
No activity |
Yes |
|
Aug 3 |
Meeting at PM-Demil to discuss
options |
Yes |
|
Aug 10 |
No activity |
Yes |
|
Aug 17 |
No activity |
Yes |
|
Aug 24 |
No activity |
Yes |
|
Aug 31 |
No activity |
Yes |
Additional
weeks to be added later as project concludes