MCAAP MCDF Messages
Web-Site Messages
|
Message ID |
Message Content |
Date Posted |
|
|
|
|
|
1 |
New format of MCAAP MCDF Website |
|
|
2 |
Staubli was scheduled to be onsite on June 6 – postpone to July 12 |
|
|
3 |
SNL scheduled for ADAM AP tests on Oct 8 |
|
|
4 |
GA/CVE will implement Air Dryer and UPS install on Oct 29 |
|
|
5 |
MCAAP APE-1236 RATA tests scheduled for Sept 24 |
09/03/07 |
|
6 |
Induction heater tests scrubbed due to problems with APE-1236 – tests rescheduled during week of 9/17/07 |
09/09/07 |
|
7 |
Air dryer installed at MCAAP |
|
|
8 |
UPS at the site – UPS installed in Electric Room |
02/22/08 |
|
9 |
Download WorkCell system will NOT be used – MQS and FTS systems will be offline |
01/14/09 |