Project Status
MCAAP MCDF Project Summary
Status
|
Effort |
Start |
End |
% Comp |
Comments |
|
|
|
|
|
|
|
Cryofracture |
|
|
|
|
|
Equipment Procurement |
Jan 2002 |
May 2003 |
100 |
|
|
Building Construction |
Jun 2002 |
May 2003 |
100 |
|
|
APE-1236 M2 Upgrades |
Dec 2002 |
June 2003 |
100 |
|
|
Installation |
Jan 2003 |
Sept 2003 |
100 |
|
|
Checkout/Startup Run in Air Run with inert mines Run with ADAM QA Run with ADAM AP |
Sept 2003 Sept 2003 Oct 2003 May 2004 |
Sept 2003 Oct 2003 Apr 2004 June 2004 |
100 100 100 100 |
|
|
Training |
Aug 2003 |
June 2004 |
100 |
|
|
Dem/Val Test |
June 2004 |
June 2004 |
100 |
|
|
|
|
|
|
|
|
PDWC (Conveyors &
Transfer) |
|
|
|
|
|
Installation |
Jul 2004 |
Sep 2004 |
100 |
|
|
Checkout/Startup |
Sep 2004 |
Oct 2004 |
100 |
|
|
Integrated Test |
Oct 2004 |
Nov 2004 |
100 |
|
|
|
|
|
|
|
|
PDWC (Robots & End
Effectors) |
|
|
|
|
|
Testing at SNL |
Dec 2004 |
Dec 2004 |
100 |
|
|
Shipping |
Mar 2005 |
Apr 2005 |
100 |
|
|
Installation |
Mar 2005 |
Sep 2005 |
100 |
|
|
Checkout/Startup |
Sep 2005 |
Nov 2005 |
100 |
|
|
ADAM QA Tests |
Jan 2006 |
Jun 2007 |
100 |
|
|
ADAM AP Tests |
Jul 2007 |
Jan 2008 |
100 |
|
|
|
|
|
|
|
|
Cryofracture
Upgrade |
|
|
|
|
|
Tooling Verification Test |
May 2005 |
Oct 2005 |
100 |
|
|
Final Design |
Nov 2005 |
Mar 2006 |
100 |
|
|
Final review and HAZOP |
May 2006 |
May 2006 |
100 |
|
|
Procurement |
May 2006 |
Mar 2007 |
100 |
|
|
Ship and Install |
Mar 2007 |
July 2007 |
100 |
|
|
Checkout/Startup |
Aug 2007 |
Sept 2007 |
100 |
|
|
Integrated Test (Inerts) |
Sept 2007 |
Sept 2007 |
100 |
|
|
Integrated Test (ADAM QA’s) |
Oct 2007 |
Mar 2008 |
100 |
|
|
Integrated Test (ADAM AP’s) |
Mar 2008 |
Apr 2008 |
100 |
|
|
|
|
|
|
|
MCAAP MCDF Project Summary
Status
|
Effort |
Start |
End |
% Comp |
Comments |
|
|
|
|
|
|
|
Cryofracture
Upgrade |
|
|
|
|
|
Upgrade Design |
Dec 2008 |
Feb 2009 |
100 |
Complete |
|
Upgrade
Procurement |
Jan 2009 |
Apr 2009 |
100 |
Complete |
|
Shipment to
MCAAP |
Apr 2009 |
Apr 2009 |
100 |
Complete |
|
Installation |
Apr 2009 |
Apr 2009 |
100 |
Complete |
|
Checkout/Startup |
Apr 2009 |
May 2009 |
100 |
Complete |
|
Integrated Test
(Inerts) |
June 2009 |
June 2009 |
100 |
Complete |
|
Integrated Test (ADAM
QA) |
June 2009 |
June 2009 |
100 |
Complete |
|
Integrated test (ADAM
AP) |
June 2009 |
June 2009 |
100 |
Complete |
|
MCAAP APE-1236
CPT |
June 2009 |
July 2009 |
100 |
Complete |
|
Integrated test (ADAM
AP) |
July 2009 |
July 2009 |
100 |
Complete |
|
Dem/Val Test |
July 2009 |
Aug 2009 |
20 |
Halted |
|
|
|
|
|
|
|
Process Drums from 2004 |
Nov 2007 |
Apr 2008 |
100 |
Processed all drums |