Project Status

 

    MCAAP MCDF Project Summary Status

Effort

Start

End

% Comp

Comments

 

 

 

 

 

Cryofracture

 

 

 

 

  Equipment Procurement

Jan 2002

May 2003

100

 

  Building Construction

Jun 2002

May 2003

100

 

  APE-1236 M2 Upgrades

Dec 2002

June 2003

100

 

  Installation

Jan 2003

Sept 2003

100

 

  Checkout/Startup

      Run in Air

      Run with inert mines

      Run with ADAM QA

      Run with ADAM AP

 

Sept 2003

Sept 2003

Oct 2003

May 2004

 

Sept 2003

Oct 2003

Apr 2004

June 2004

 

100

100

100

100

 

 

 

 

 

  Training

Aug 2003

June 2004

100

 

  Dem/Val Test

June 2004

June 2004

100

 

 

 

 

 

 

PDWC

(Conveyors & Transfer)

 

 

 

 

  Installation

Jul 2004

Sep 2004

100

 

  Checkout/Startup

Sep 2004

Oct 2004

100

 

  Integrated Test

Oct 2004

Nov 2004

100

 

 

 

 

 

 

PDWC

(Robots & End Effectors)

 

 

 

 

  Testing at SNL

Dec 2004

Dec 2004

100

 

  Shipping

Mar 2005

Apr 2005

100

 

  Installation

Mar 2005

Sep 2005

100 

 

  Checkout/Startup

Sep 2005

Nov 2005

100

 

  ADAM QA Tests

Jan 2006

Jun 2007

100

 

  ADAM AP Tests

Jul 2007

Jan 2008

100

 

 

 

 

 

 

Cryofracture Upgrade

 

 

 

 

  Tooling Verification Test

May 2005

Oct 2005

100

 

  Final Design

Nov 2005

Mar 2006

100

 

  Final review and HAZOP

May 2006

May 2006

100

 

  Procurement

May 2006

Mar 2007

100

 

  Ship and Install

Mar 2007

July 2007

100

 

  Checkout/Startup

Aug 2007

Sept 2007

100

 

  Integrated Test (Inerts)

Sept 2007

Sept 2007

100

 

  Integrated Test (ADAM QA’s)

Oct 2007

Mar 2008

100

 

  Integrated Test (ADAM AP’s)

Mar 2008

Apr 2008

 100

 

 

 

 

 

 

 

 

 

 

 

 

 

    MCAAP MCDF Project Summary Status

Effort

Start

End

% Comp

Comments

 

 

 

 

 

Cryofracture Upgrade

 

 

 

 

    Upgrade Design

Dec 2008

Feb 2009

100

Complete

    Upgrade Procurement

Jan 2009

Apr 2009

100

Complete

    Shipment to MCAAP

Apr 2009

Apr 2009

100

Complete

    Installation

Apr 2009

Apr 2009

100

Complete

    Checkout/Startup

Apr 2009

May 2009

100

Complete

    Integrated Test (Inerts)

June 2009

June 2009

100

Complete

    Integrated Test (ADAM QA)

June 2009

June 2009

100

Complete

    Integrated test (ADAM AP)

June 2009

June 2009

100

Complete

    MCAAP APE-1236 CPT

June 2009

July 2009

100

Complete

    Integrated test (ADAM AP)

July 2009

July 2009

100

Complete

    Dem/Val Test

July 2009

Aug 2009

20

Halted

 

 

 

 

 

Process Drums from 2004

Nov 2007

Apr 2008

100

Processed all drums